Enough DCR Cells for 2027? ALMM List-II Supply Check
Market & Policy

Enough DCR Cells for 2027? ALMM List-II Supply Check

Shashank·Founder·November 19, 2026·6 min read

The Question

Until December 31, 2026, net-metering and open-access projects can still use cells from outside the list. From January 1, 2027 they cannot, which puts them under the same rule as government tenders and subsidy schemes. The useful question for a buyer is not who is on the list but whether the list can supply the volume.

This piece does the arithmetic. It does not forecast prices or shortages. Our ALMM List-II guide covers who is listed and our Non-DCR guide covers the rules.

The Inputs

Item

Figure

Listed cell capacity, 13th revision

44,859 MW a year

Solar added, January to October 2026

38.7 GW

Average monthly additions, January to October

3.87 GW

Solar added in October 2026

3.50 GW

Annualized pace of additions

46.5 GW

Grid-connected rooftop added, November 2025 to October 2026

11.8 GW

Annualized rooftop pace

12.9 GW

Cell and module capacity are both counted in gigawatts of DC capacity, so one gigawatt of listed cells supports roughly one gigawatt of modules. The additions come from MNRE's monthly capacity data, which splits solar into ground-mounted, rooftop, hybrid and off-grid but not by compliance category.

The Arithmetic

Listed capacity is nameplate. A factory rarely runs at full output, so the table shows three utilization levels against two demand cases.

Utilization

Listed cells

Covers all additions (46.5 GW)

Covers rooftop only (12.9 GW)

100%

44.9 GW

96%, gap of 1.6 GW

348%

80%

35.9 GW

77%, gap of 10.6 GW

279%

60%

26.9 GW

58%, gap of 19.6 GW

209%

Put the other way, listed capacity equals about 11.6 months of additions at the 2026 pace.

Reading the Table

  • The top bound cannot be met. Covering every project from listed cells would take about 104% utilization, so some supply would have to come from outside the list or from new capacity.
  • The bottom bound is comfortable. Rooftop alone needs only about 29% of listed capacity.
  • The truth depends on the mix. Government tenders and subsidy schemes are already covered. The newly covered pool from January 1 is net-metering and open-access projects, and MNRE's monthly data does not say how large it is.

What Could Tilt the Answer

  • Output against nameplate. Enlisted capacity includes lines that are still ramping. The 13th revision alone added 7,063 MW, about 1.8 months of 2026-pace additions, and the list has grown by 18,068 MW since the 4th revision.
  • The December rush. Projects with exempt supply may commission before December 31 using non-listed cells, which would pull demand forward and ease the pressure in early 2027.
  • Exports. Some listed capacity may go to export markets, which would reduce what is left for India.
  • Other estimates. Wood Mackenzie's August projection of 29 GW of domestic cell output against about 50 GW of annual module demand points to a tighter picture than nameplate does. Our anti-dumping guide has the detail. Manufacturing additions in the first half of 2026 were 9.7 GW of cells against 50.6 GW of modules, so cells are still catching up.

What EPCs Can Do With This

  • Ask suppliers for volume and dates. A listed manufacturer's capacity is not your capacity. Ask for cell supply in megawatts and delivery months against your order book.
  • Check your own mix. Work out how much of your 2027 pipeline falls under the net-metering and open-access exemption that ends on December 31, because that is the demand that is new to the list.
  • Watch two numbers. MNRE's monthly additions and each List-II revision tell you whether supply is keeping pace. The cell side needs to grow faster than the monthly additions to ease the squeeze.
book a demo

Where Design Software Fits

Cell supply shows up in procurement as a line in the bill of materials. Design software like Reslink produces the bill of materials with ALMM flags, so the module and cell model sits in the same document as the design. It does not decide compliance or secure supply.

See the full workflow → Book a demo

Frequently Asked Questions

Q1. Is there enough ALMM List-II cell capacity for 2027?

On paper it is close. Listed capacity of 44.9 GW covers 96% of 2026-pace additions at full output, and less at realistic utilization. Not every project falls under the list.

Q2. How much cell capacity does List-II have?

44,859 MW a year after the 13th revision on October 28, 2026.

Q3. How much solar does India add each month?

About 3.5 GW in October 2026 and 3.87 GW a month on average from January to October.

Q4. What utilization would cover all solar additions?

About 104% at the 2026 pace, so listed capacity alone cannot cover every project. Rooftop alone needs under 30%.

Q5. Do all projects need List-II cells from January 1, 2027?

The net-metering and open-access exemption ends on December 31, 2026, so those projects join the covered pool. Which projects are covered depends on the category, so check it against our Non-DCR guide.

Q6. Why do cell supply estimates differ?

They measure different things: nameplate capacity on the list, actual output, or projections. Wood Mackenzie's 29 GW is a projection of output.

Q7. What should I watch?

MNRE's monthly solar additions and each List-II revision, which show whether listed capacity is growing faster than demand.

Final takeaway

Listed cell capacity is enough to cover rooftop demand several times over, and not enough to cover all solar demand at a realistic utilization. The January 1 exemption change will decide how much of the wider market lands on the list. Treat cell supply as a procurement risk to price and plan for, not as a certainty either way.

You May Also Like

Sources

This analysis uses published capacity and installation figures as of November 19, 2026. Figures change with each MNRE update and List-II revision, and the arithmetic is an illustration of scale, not a forecast.

#ALMM List-II cell capacity#DCR solar cells 2027#India solar cell supply demand#ALMM exemption December 31 2026#India solar additions 2026

Reslink Presents

The New Age Of Solar With Just One Workflow

Everything your team needs, from site visualization to bankable design and documents, all in one place.

Ready To See Reslink In Action?

Join 6000+ solar EPCs already designing, proposing, and closing faster with Reslink.

Talk to sales